some of Our Projects:

M5 Bidston MossHE - Maintenance Areas 7 & 12HA - Amey Area 9 Tesco Stores New build programmeCTRL 588 - Emcor rail

M5 - Bidston Moss

The Challenge

Deliver aggressive programme & productivity outputs on a logistically constrained £96m bridge refurbishment

Our Approach

Deploy:

  • Collaborative planning approach
  • Navitas Implementation Leader to support
  • Supporting PDCA software

Deliver a self sustaining, self improving build team

Our Results

  •  £ 7.2m overall savings on £96m target cost against top quartile cost challenges
  • Project delivered 4 weeks early against aggressive programme
  • ‘Difficult’ tier 2 contractors engaged & bought in to process
  • Self-sustaining improvement culture embedded

Reference

Adam Bennett - Highways Head of CI  adam.bennett@costain.com 

Ha - Amey Area 9

The Challenge

Deliver 20% cost & time savings on £15m of annual design in 12/13 cycle

Our Approach

  Deploy:

  • Collaborative Planning approach 
  • Navitas Implementation Leader to support
  • Supporting PDCA software

Deliver a self-sustaining, self-improving design team

Our Results

  • £ 5.1m overall savings to be delivered over remaining 1.5 years of contract - 2012/14
  • Design delivery improved by 25% in absolute time terms
  • Design team self-sustaining in their implementation of collaborative planning

Reference

Carl Hayward - Head of CI 

carl.hayward@amey.co.uk

HE - Maintenance Areas 7&12

The Challenge

Improve productivity & reliability of delivery & spend on 350no project portfolio in design/price/mobilise phase

Our Approach

Deploy:

  • Collaborative planning approach
  • Navitas Implementation Leader to support
  • Supporting PDCA software

Develop self-sustaining improvement culture

Our Results

  •   37% improvement in scheme delivery on time / early over 6 month period
  • Task reliability improved by 46% over same period
  • £ 5.04m of savings on scheme portfolio
  • Team re-built & bonded – collaboration underpinned

Reference

Neal Symmons - HE Lean Lead - neal.symmons@highwaysengland.co.uk


Tesco Stores New Build Programme

The Challenge

Demonstrate opportunity to save 30% on time & 20% on cost on Tesco new build stores programme

Our Approach

  Deploy:

  • Collaborative Planning approach 
  • 3D / 4D tools & techniques
  • Navitas Implementation Leader to support
  • Supporting PDCA & 3D software

Our Results

  • 30% improvement in task reliability in 12 weeks
  • Clear benefits opportunity identified
  • 30no sub-contractors integrated at task level
  • Clear improvement opportunities identified
  • Improved relations between Tiers 1 & 2

Reference

Joanne Neville (Head of Delivery Tesco Ireland) - joanne.neville@ie.tesco.com

CTRL 588 -Emcor Rail

The Challenge

Improve productivity on 42km of head-house & portal project in a 3 monthwindow (220no + workforce – direct & subs)

Our Approach

  Deploy:

  • Collaborative Planning approach 
  • Navitas Implementation Leader to support
  • Supporting PDCA 

Develop self-sustaining improvement culture

Our Results

  • 30% improvement in task reliability in 12 weeks
  • 40% improvement in productivity in same period
  • Transparency of issues on site – clear line of sight for improvement effort
  • Team re-built & bonded – collaboration underpinned

Reference

Chris Raven (MD Bailey Rail)

chris.raven@ngbailey.co.uk

Copyright © 2025 Navitas Project Solutions - All Rights Reserved.

  • Privacy Policy

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

DeclineAccept